Griesbach is a residential subdivision development at the former military base, we removed existing infrastructure and installed new water and sewer mains and pre-graded the road for paving.
Scope of work
Client:
Canada Lands
Project Location:
108 Street and Sir Arthur Currie Way, Edmonton AB
Major Quantities:
2780m of pipe
99 services
16 Catch Basins
Work Commenced:
May 1, 2018
Work Completed:
July 3, 2018 – Our work completed, subs were on site until October