Planning

Thompson Infrastructure Ltd. (TIL) was awarded the Town of Wainwright Sanitary Lift Station and Gravity Trunk Main project in spring 2020. The scope included excavation and installation of an 11m deep lift station with corresponding gravity and forced sewer mains through both greenfield and existing roads. As the General and Prime Contractor, TIL coordinated the completion of surface works restoration as well as all mechanical requirements for the lift station.

Scope of work

Client:
Town of Wainwright

Project Location:
Wainwright, Alberta

Major Quantities:

  • Supply & Install a new pre-cast Sewer lift station (11M Depth) along
  • Installed approx. 400LM of Gravity Sewer Trunk Line by open cut (4-7M Depth)

Work Commenced:
September 2020

Work Completed:
On going

 

 

3000+

Man Hours to Date

September 2020

Work started

Ongoing

Work Completed