Planning
This project consisted of construction of the East Athabasca Highway including several bridges and bridge culverts.
Scope of work
Client:
Suncor Energy
Project Location:
100 km Northeast of Fort McMurray, Alberta
Major Quantities:
- Grading, Base Course and Lean Oil Sands Construction
- Material handling and staging
- Highway Construction – Common / Borrow / Channel topsoil Excavations
- Grading, Base Course and Lean Oil Sands Construction
- Geotextiles, Culverts, Graveling, Signage and Seeding
- 3 Bridges / Bridge Culvert Construction – 7 Creek Crossings
- Channel Excavation, Frainage Culverts and Erosion Control
Work Commenced:
October 2009
Work Completed:
December 2010