Planning

Thompson Infrastructure was selected by the City of Fort Saskatchewan as the General Contractor to rehabilitate 3 blocks of existing downtown roadway and services to bring the underground facilities and roadways up to current construction standards. The redevelopment required rigorous phasing and scheduling, ensuring project milestone are met on time to guarantee residents would have minimal impact during construction over the course of the project

Scope of work

Client:
City of Fort Saskatchewan

Project Location:
108 Street 102 Avenue

Major Quantities:

  • 1.1 km of Underground Mainline Replacement
  • 34 Services
  • 3 Blocks (6,200m2) of New Roadway

Work Commenced:
June 2021

Work Completed:
On going